Vleugels van Hoop

 
Vleugels van Hoop
 
Welcome - Who are we? - How to help? - Projects - Actions - Press New - Contact us - FAQ

 

 

 


CRVO Uganda 2022
Follow-up 2022
Follow-up jan. 2023
Images

 

 

 

 

 

Water tanks households

Location:               Kabale - Uganda

Project leadtime:   2 months

Requestor:           Tumwesigye Leonard on behalf of Children Rescue Voluntary
                              Organisation (CRVO)

Description of the project:

Water in life is an important necessity for meaningful and health of our children and their communities. Many children don’t get clean water and the distance to water sources is long.

Objectives:

  • To reduce the burden of children to walk long distances for fetch water
  • To reduce diseases due to drinking unclean water
  • To reduce the risks the small children undergo while walking to the water sources

Beneficiaries:

  • 35 homes of vulnerable children under CRVO and their households
  • homes of children who’s guardians (single mothers) are chronically ill

Budget:

The budget for 35 water jars will be 35.000.000 Uganda Shillings.

Risks:

Only risks are the strongly hiking of prices in case implementation would be delayed.

Attached documents:

Detailed budget overview

Top


Follow-up of the project

Date:                    October 20th 2022
 
Name project:       Water tanks households

General status:

After arrival of funds September 1st the implementation team gathered and started the project by purchasing all needed materials. On September 7th all materials were distributed to all houses. Since then, there has been close monitoring of the guardian’s representatives and the CRVO staff to ensure that good work is done. Today a total of 20 tanks have been completed and we hope by 7th November all the targeted beneficiaries will be equipped with water harvesting tanks.

Progress since last status report:

Since the start of this project there has been steady progress as each family actively participated in ensuring that the needed materials are carried from where the road stops to their hilly places .This indeed helped the contractor and his staff to work day and night in order to finish the work within the agreed time frame. Each water harvesting tank has a capacity of 1200 litres that is equivalent to 60 jerrycans of water.

Financial status:

This project was budgeted at a total cost of 35.000.000 Uganda shillings and all expenditures have been done accordingly.

Problems/concerns:

The challenges encountered during the implementation of this project were
- hiked prices
- hard to reach some of the houses
- transport challenges due to poor roads

Attached documents (pictures, receipts,…):

Receipts and pictures

Top


Follow-up jan. 2023

Date:                    January 27th, 2023
 
Name project:       Water tanks households

General status:

This project started with arrival of funds on our account on September 1st ,2022.
The work started with purchasing of all the needed materials and started officiary on September 7th after all the materials needed were fully transported to the different homes. The beneficiaries actively participated in carrying some of the materials to the different homes as the lorry transport could not reach the homes. There has been close monitoring of the guardians’ representatives and the CRVO staff to ensure that good work is done. A total of 35 tanks have been completed as per our earlier plan.

Progress since last status report:

There has been steady progress as each family actively participated in ensuring that the needed materials are carried from where the road stops to their hilly places. This indeed helped the contractor and his staff to work night and day in order to finish the work within the agreed time. All 35 families have so far received tanks. Each water harvesting tank has a capacity of 1200 liters that is equivalent to 60 jerry cans of water.

Financial status:

This project was budgeted at a total cost of 35.000.000 Uganda shillings and all expenditures have been done accordingly.
According to the above, the lead time was two months, and the work was well done as planned. Hence a completed project.

Problems/concerns:

There were several challenges encountered during the implementation of this project such as
- impassable paths due to hills
- poor network
- many homes are scattered
- hiked prices of food
- transport challenges due to poor roads.

Attached documents (pictures, receipts,…):

receipts, pictures.

Top


Images

Clic on the image to see the whole album

Top