Construction of a centre for disabled children - phase 1

Location: Nyacyonga, district Gasabo

Project leadtime: 1 year

Requestor: Didier SEMANYENZI on behalf of Jya Mu Bandi Mwana

Description of the project:

The current centre for disabled children Karuruma is situated in a (rental) house. This is a temporary solution, as the type of rooms is not in line with the norms. Earlier the building was adapted where needed, with the help of Vleugels van Hoop vzw. On the other hand there is a huge lack of space and the targeted needs are not covered.

Today they have to leave... they are pushed on the street!

There is 1 sparkle of hope though!
An international organisation donated a piece of land to Jya Mu Bandi Mwana.
The construction plans are ready though the needed funds are not available.

The overall construction project will be spread over 3 years. Seen the needed funds the project will be split in 3 phases.

Objectives:

The objectives of the 1st phase are:

  • Preparation of the site
  • Construction of 3 classrooms
  • Construction of toilets next to the classes
  • Construction of the refectory and kitchen
  • Construction of the office and a room for physical therapy
  • Construction of 2 dormitories (girls and boys)
  • Construction of a sanitary block with toilets and showers

Budget:

The budget for phase 1is 27.778.500 RwFr, which is about € 29.850 (exchange rate May 15th 2014)

 

Budget

Contribution of
Jya Mu Bandi Mwana

Financial request towards Vleugels van Hoop vzw

Preparational works

2.948.000

0

2.948.000

3 classrooms

6.345.000

257.000

6.088.000

Toilets next to the classes

1.200.000

200.000

1.000.000

Refectory and kitchen

4.650.000

350.000

4.300.000

Office and room for physical therapy

3.960.000

60.000

3.900.000

2 dormitories

7.146.000

106.000

7.040.000

Sanitary block (toilets and showers)

2.852.500

350.000

2.502.500

Total (RwFr)

29.101.500

1.323.000

27.778.500

Risks:

Attached documents:

Prove of ownership of the land

Top


Follow-up of the project

Date: August 8th 2014

General status:

Since the beginning of juni 2014, Jya Mu Bandi Mwana is doing, with the financial support of Vleugels van Hoop, the construction works for the centre for disabled children. These works have started with the installation of the yard and listing all needed materials. At the moment (beginning of Aug.’14) the preparational activities are finalised, water and electricity are under construction, the preparation of the site is done so now the real construction activities can start, i.e. foundations, build up and place the roof construction.

Progress since last status report:

The executed preparational activities executed during the past 2 months are:
- signing the agreement for installation of water and electricity by the competent suppliers
- purchase of materials like mattocks, heels,…
- preparation of the site is almost completed
- a storage space was build and a toilet is foreseen
The site work are evolving well and will be completed by mid of August.

Financial status:

Financing & realised expenditures during Phase 1  (beginning Aug. 2014)
Own contribution of the association (include. purchase of site) 21.300.000 Purchase site 20.000.000
Support from
Vleugels Van Hoop
27.778.500 Expenditures till August 1st 2014 3.885.000
Total 49.101.500   23.885.000
    Balance 25.216.500

Problems/concerns:

Delays water company: 
Water is crucial, a basic need for construction works. We had to wait for the signing of the agreement to foresee the supply to the site. A yard tank was installed to not hinder the works in the future.
 
Long period of preparing the site:
Removal of roots and rocks took longer than planned for. Indeed, part of the site was bush in the past (long, deep roots).

Review of the work plan in line with the remarks of the urban authority of the city Kigali:
On Juli 25th 2014, the site was visited by relevant authorities. When showing the work plans the advice was given to foresee the foundations fully, to later on construct the buildings module by module.

Attached documents (pictures, reçu’s,…):

Pictures

Top


Images

Album start Click here

Top


Follow-up december 2014

Date: December 8th 2014
 
Name project: Project 54 A: Construction project Jya mu bandi mwana – phase 1

General status:

On December 7th the board of Vleugels van Hoop visited the construction project in Jali, Rwanda.
On December 8th the ceremony of putting the first stone was done by the Ambassador of Belgium, the mayor of Kigali and the president of Vleugels van Hoop, in the presence of a big part of the children.

Progress since last status report:

All foundation works are completed, except for the office and the kine space, and the building of the refectory/kitchen and the 3 classrooms is progressing very smooth. An excellent achievement!

Soon phase 2 will be started which will be discussed on a meeting on December 12th, between the project responsible persons and the board of Vleugels van Hoop.

Financial status:

The provided funds are fully consumed as planned. The invoices were handed over on December 12th.

Problems/concerns:

None

Attached documents (pictures, reçu’s,…):

Pictures and Invoices