Location: Nyacyonga, district Gasabo Project leadtime: 1 year Requestor: Didier SEMANYENZI on behalf of Jya Mu Bandi Mwana Description of the project: The current centre for disabled children Karuruma is situated in a (rental) house. This is a temporary solution, as the type of rooms is not in line with the norms. Earlier the building was adapted where needed, with the help of Vleugels van Hoop vzw. On the other hand there is a huge lack of space and the targeted needs are not covered. Today they have to leave... they are pushed on the street! There is 1 sparkle of hope though! The overall construction project will be spread over 3 years. Seen the needed funds the project will be split in 3 phases. Objectives: The objectives of the 1st phase are:
Budget: The budget for phase 1is 27.778.500 RwFr, which is about € 29.850 (exchange rate May 15th 2014)
Risks: Attached documents: Prove of ownership of the landFollow-up of the projectDate: August 8th 2014 General status: Since the beginning of juni 2014, Jya Mu Bandi Mwana is doing, with the financial support of Vleugels van Hoop, the construction works for the centre for disabled children. These works have started with the installation of the yard and listing all needed materials. At the moment (beginning of Aug.’14) the preparational activities are finalised, water and electricity are under construction, the preparation of the site is done so now the real construction activities can start, i.e. foundations, build up and place the roof construction. Progress since last status report: The executed preparational activities executed during the past 2 months are: Financial status:
Problems/concerns: Delays water company: Review of the work plan in line with the remarks of the urban authority of the city Kigali: Attached documents (pictures, reçu’s,…): Pictures ImagesFollow-up december 2014Date: December 8th 2014 General status: On December 7th the board of Vleugels van Hoop visited the construction project in Jali, Rwanda. Progress since last status report: All foundation works are completed, except for the office and the kine space, and the building of the refectory/kitchen and the 3 classrooms is progressing very smooth. An excellent achievement! Soon phase 2 will be started which will be discussed on a meeting on December 12th, between the project responsible persons and the board of Vleugels van Hoop. Financial status: The provided funds are fully consumed as planned. The invoices were handed over on December 12th. Problems/concerns: None Attached documents (pictures, reçu’s,…): Pictures and Invoices |