Location: Nyacyonga, district Gasabo Project leadtime: 4 months Requestor: Didier Semanyenzi on behalf of Jya Mu Bandi Mwana Description of the project: After the successful finalisation of the 3 first phases of the construction project (projects 54 A, B en C) the centre is ready to welcome the children, including the long expected provisioning of electricity. Objectives: The objectives of this 4th phase are:
Beneficiaries: 267 children at Jya mu bandi mwana Budget:
Risks: Attached documents: Detailled budget Follow-up of the projectDate: August 31st 2016 General status: At the moment we have 36 children in the new centre. 24 of them are following classes and having kiné where the others are following classes in a nearby primary school, in inclusive education. Progress since last status report: Electricity is installed in all buildings of the centre: classes, dormitories, kitchen etc. The classes are fully ready regarding painting, barza (covered terrace extending the threshold of a building), electricity etc. as well as both dormitories. The toilets and sanitary are partly done; a lavabo and English toilet are bought but not yet installed. For this we hired last week a specialist to install the tubes and the drains for waste water; he decided to make the wholes bigger; this will take somewhat more time but all should be finalized by the end of September. The kitchen and stores are almost done; remaining is the painting and purchase of cooking material etc. The pitch for sitting volleyball was not prioritized but will be done in the coming weeks. The construction of paved paths for the disabled children as well as the spot for the guard will be done simultaneously, together with the volleyball pitch, after the canalisation. Workforce Development Authority (WDA) promised to help us as long as the construction works are ongoing. We plan to have the technical school ready in January. Financial status: Problems/concerns: Attached documents (pictures, reçu’s,…) Follow-up september 2016Greetings, Follow-up october 2016Progress since last status report:
Financial status: Received funds: 31.290.550 RwFr Expenditures till end of Sept 2016:
Problems/concerns: All materials for the sanitary installation are delivered but the technician only shows up on irregular times; works needs to be finalised before end of November. Shrubs are planted around the dormitories and the refectory. Currently it is the short rainy season; therefore all is growing well. Related to the finalisation of the yard: as trucks are still driving on and off we wait for the final clean-up to start these activities. To be beneficial the biogas installation requires a higher number of habitants. We wait for the arrival of a high amount of children. ImagesClic on the image to see the whole album |