Jya Mu Bandi Mwana
Rwanda 2016 - 2
Follow-up august 2016
September 2016
October 2016
Images

 

 

 

 


Project 54 D - Construction of a centre for disabled children – phase 4     
 

Location: Nyacyonga, district Gasabo

Project leadtime: 4 months

Requestor:  Didier Semanyenzi on behalf of Jya Mu Bandi Mwana

Description of the project:

After the successful finalisation of the 3 first phases of the construction project (projects 54 A, B en C) the centre is ready to welcome the children, including the long expected provisioning of electricity.

Objectives:

The objectives of this 4th phase are:

  • Completion of the 3 classrooms, 2 dormitories and the refectory : painting the walls in-house, building sidewalks,….
  • Provisioning of electricity plugs and fuse boxes in all buildings
  • Sanitary facilities in the refectory and dormitories
  • Further construction and completion of the kitchen
  • Adjustments to the site, according the needs of the disabled children
  • Completion of the biogas facilities

Beneficiaries:

267 children at Jya mu bandi mwana

Budget:

Description

Budget in RwFr

Budget in € (+/-)

Completion classrooms

3.446.000

3.938

Completion dormitories

5.446.800

6.225

Completion refectory

4.061.600

4.642

Electricity in all buildings

1.510.100

1.726

Sanitary facilities dormitories

2.560.000

2.926

Sanitary facilities refectory

890.000

1.017

Kitchen and warehouse

3.901.050

4.458

Adjustments site

6.355.000

7.263

Biogas

3.120.000

3.566

Total

31.290.550

35.761

Risks:

Attached documents:

Detailled budget

Top


Follow-up of the project

Date: August 31st 2016
 
Name project: Project 54D – Jya mu bandi mwana – Construction project phase 4

General status:

At the moment we have 36 children in the new centre. 24 of them are following classes and having kiné where the others are following classes in a nearby primary school, in inclusive education.

Progress since last status report:

Electricity is installed in all buildings of the centre: classes, dormitories, kitchen etc. The classes are fully ready regarding painting, barza (covered terrace extending the threshold of a building), electricity etc. as well as both dormitories.

The toilets and sanitary are partly done; a lavabo and English toilet are bought but not yet installed. For this we hired last week a specialist to install the tubes and the drains for waste water; he decided to make the wholes bigger; this will take somewhat more time but all should be finalized by the end of September.

The kitchen and stores are almost done; remaining is the painting and purchase of cooking material etc.
 
For the garden and the fence we wait for the rainy season so trees have sufficient water. The fence with shrubs is ready, remaining are the trees to be planted along.

The pitch for sitting volleyball was not prioritized but will be done in the coming weeks. The construction of paved paths for the disabled children as well as the spot for the guard will be done simultaneously, together with the volleyball pitch, after the canalisation.
Same for the divers: a concrete water tank and the biogas installation.

Workforce Development Authority (WDA) promised to help us as long as the construction works are ongoing. We plan to have the technical school ready in January.

Financial status:

Problems/concerns:

Attached documents (pictures, reçu’s,…)

Top


Follow-up september 2016

Greetings,

Excuse for the delay. Since this morning there were problems with the internet connection.
Last time I sent some pictures, maybe you didn’t receive them. Currently I sent you other photo material. This shows the current situation in the Centre JMBM. Some pictures of the covered galleries will follow. Furthermore, the work on electricity is finished. Several works are ongoing, we shall now proceed with the tiling of the paths and the electrical installation in all rooms.
It is always a pleasure to be able to work together with you. Thank you very much for that! Xavérine, coordinator.

Top


Follow-up october 2016

Progress since last status report:

Activities

Realisation (yes/no/ongoing)

Remarks

Painting inner walls

Ongoing

Materials have been purchased – classrooms OK – soon dormitories and refectory

Repointing outer walls and checks of pillars

Ongoing

Still a small surface needs to be treated

Pavements and covers (roofs)

Yes

OK

Electricity installation in all buildings

Yes

OK

Sanitary for dormitories and refectory

Ongoing

Materials delivered – Installation planned soon

Construction of the kitchen

Ongoing

Remaining is windows and kitchen equipment

Closure and outside site finishing

Ongoing

Closure OK – Garden not finalised as trucks are still driving on and off

Installation biogas

No

Installation will be done when high amount of children return

Financial status:

Received funds: 31.290.550 RwFr

Expenditures till end of Sept 2016:

  Amount
Working hours 5.317.600
Painting inner walls 2.110.000
Repointing outer walls and checks of pillars 5.240.000
Pavements and covers (roofs)     1.510.000
Electricity installation in all buildings 2.910.000
Construction of the kitchen 3.118.050
Closure and outside site finishing 2.355.000
Total 22.560.750

Problems/concerns:

All materials for the sanitary installation are delivered but the technician only shows up on irregular times; works needs to be finalised before end of November.

Shrubs are planted around the dormitories and the refectory. Currently it is the short rainy season; therefore all is growing well. Related to the finalisation of the yard: as trucks are still driving on and off we wait for the final clean-up to start these activities.

To be beneficial the biogas installation requires a higher number of habitants. We wait for the arrival of a high amount of children.