Twese Hamwe 2008
|
|
With all pleasure we present you a project which we will support in 2008:
Socio cultural centre TWESE HAMWE
KIGALI - RWANDA
Purification & canalisation of rain water in the socio cultural centre Twese Hamwe
1.Presentation of the project
- beneficiary organisation
Socio Cultural Centre Twese Hamwe
1.2.Name
Purification & canalisation of rain water
1.3.Location
District of Kacyiru
Agglomeration Kigali city
1.4. Contact persons
Bernadette UMURERWA
Wally NYINAWAYUHI
Evariste NIKOLAKIS
Jean-Paul VAN STEEN
2. Description
The city of Kigali donated tp Twese Hamwe an area of approximately ½ ha in order to develop several projects for the benefit of a vulnerable part of the population.
This plot is situated on a hillock with a slope degree of +/- 5%.
Rain water, for the biggest part coming from 200 surrounding rural entities, has full ‘freedom’ giving a catastrophic impact.
The area damaged by erosion moreover is a threat to the game and sport of the children.
This project strives for the canalisation of the rain water over a length van120 meters and therefore pipes with a diameter of 90cm and length of 1m will be used
2. Duration time
Planned duration time for the realisation of this project is 3 months.
3. Budget
Purpose |
Unit |
Quantity |
Unit price in RwFr |
Total in RwFr |
I Groundworks |
|
|
|
|
Analyse and dig up |
|
|
|
500,000 |
II Constructionwork |
|
|
|
|
Piping / 4 regards |
|
|
|
|
1 Pipes |
|
120 |
50,000 |
6,000,000 |
2 Transport |
|
|
|
200,000 |
3 Moellons |
truck |
6 |
45,000 |
270,000 |
4 Sand |
truck |
4 |
40,000 |
160,000 |
5 Grint |
truck |
4 |
40,000 |
160,000 |
6 Concrete |
bag |
150 |
11,000 |
1,650,000 |
7 Beams |
piece |
100 |
4,500 |
450,000 |
8 Nails |
kg |
12 |
1,000 |
12,000 |
Hour remunerations |
|
|
|
2,000,000 |
Sub-total |
|
|
|
10,902,000 |
Total |
|
|
|
RwFr 11,402,000 |
11,402,000 RwFr = € 15.000 |
We sincerely thank you in advance for:
your gift: large or small..... on bank account 001-5300142-41 of vzw “Wings of Hope”
Communication: Twese Hamwe 2008 - project rain water
Top
Follow-up of the project
Action plan 2008
1. Introduction
In 2008 Twese Hamwe exists for 10 years.
We reached so far 400 families:
- Literacy of children below 15 year
- Literacy of adults
- Sewing education
- Cultivation of ewes
- Green brigades project
- Textile painting project
We quote as well the 2005 sewing workshop project with 10 finalists. Each of them got a sewing machine on credit. All of them are paid back by now. This group although didn’t keep on working together. From this we learned that the team work also needs to be framed. Therefore the group textile painting works under the guidance of the Centre.
2. Planned activities
- Prolongation of the 2007 projects
- Sewing education
- Literacy for adults
- Green brigades: we think to start the waste products treatment in 2008, on the condition we find a suitable place outside the city.
- Textile painting: Thanks for the sewing project we believe to be able to finance the purchasing of the tissues to paint and to explore the selling of these tissues
- Household education / hotel trade : To start with 2 groups in January 2008 :
- Before noon : for the unemployed youngsters who want to learn a profession
- In the afternoon : for those having a profession but didn’t had the official education, as extra schooling
3. Budgeting 2008
Functioning costs
N° |
Category |
Yearly amount |
1 |
Personnel |
3.200.000 |
2 |
Common costs |
720.000 |
3 |
Administration |
500.000 |
4 |
Bank fees |
20.000 |
5 |
Office equipment |
1.200.000 |
6 |
Water, electricity |
500.000 |
Total |
|
6.140.000 |
Projects 2008
N° |
Project |
Amount |
Financial source |
1 |
Household education |
12.478.900 frw |
financing partly finalized |
2 |
Canalisation of water |
11.402.000 frw |
Still searching for finances |
3 |
Textile painting & confection |
5.000.000 frw |
Searching for finances |
Top
|
|